Beginning this Friday, January 9th, work will begin on the removal and paving of a 200 Ft x 20 Ft section of West Creek Lane.

  • January 9th – The 200 ft x 20 ft section being replaced will be saw cut in preparation for removal
  • January 12th – Removal of the 1/2 if the Saw cut sections (100 ft long x 10 ft wide)
  • January 13th – New section (1/2) will be poured in concrete
    • It will take 3 or 4 days to properly cure. No one may drive or walk on this section until it is fully cured
  • January 19th – Second section will be removed
  • January 20th – New section (other 1/2) will be poured
    • It will take 3 or 4 days to properly cure. No one may drive or walk on this section until it is fully cured

We will put out written notices of this schedule to all addresses affected by this street replacement and will also make arrangements for those affected to have somewhere to park their vehicles.